Beachfields Leisure Centre: Project Update

Last week, Chris Parrish visited Beachfields to check progress as the transformation continues at pace.

Key Milestones Achieved

  • Internal demolition of the existing building is now complete, preparing the site for the next stages.
  • A client finishes meeting allowed stakeholders to review samples and get a feel for the final look of the centre.
  • The new extension is taking shape: foundations, ground beams, and below-ground waterproofing are complete, the full ground floor slab has been poured, and internal partitions within the existing building are beginning to rise.

 

Collaborative Effort
Exciting progress has been made thanks to the hard work of everyone involved: Alliance Leisure, Etec Group, Swale Borough Council, Sheppey Matters, Serco, Engenuiti, Osborn Associates, Varsity Consulting.